Where Developers Try to Lease Public Land to Build Data Centers

More than a dozen large public lands may be part of the United States’ arsenal in the global race for artificial intelligence supremacy.

The Bureau of Land Management and the Department of Energy are considering leasing at least 17 public lands totaling 19,200 acres to developers who plan to build data centers and electrical infrastructure on the land, a Bisnow analysis of public records found. Just two companies are responsible for more than half of the filings.

“This is a new strategy by the Trump administration,” said Chinonso Anozie, an assistant professor at the University of Houston Law Center. “What we’re going to do is remove a lot of local opposition and local vetoes in some of these data centers, limiting what the state and local communities can do to challenge and stop data centers.”

Flickr/Bureau of Land Management

Morley Nelson Snake River Birds of Prey National Conservation Area in Idaho, where the Bureau of Land Management is considering leasing public land for data center development.

Bisnow verified 17 projects proposed with BLM and DOE that are either approved or awaiting authorization by cross-referencing Federal agency records and press releases with tracking data centers from two conservation and public lands advocacy groups: Western Priority Center and More Than Just Parks.

The majority of these projects, excluding separate parcels of land for power plants, are located in the western part of the US, while some sites are located in the southeast.

The filing shows that developers jumped at the chance to lease public land, catalyzed by the White House’s July 2025 initiative to accelerate the nation’s AI industry and by last year’s One Big Beautiful Bill Act.

Using public land also means the federal government can bend the supremacy clause, a constitutional provision that gives federal law priority over some state laws. This tool can help developers to fight data centers.

Industry advocacy group the Data Center Coalition praised the Trump administration and the DOE for the policy initiative.

“The digital infrastructure that data centers provide is critical to improving America’s global economic competitiveness, maintaining national security, and maintaining the nation’s edge in cloud computing, artificial intelligence, and many other 21st century technologies,” said Michele Nellenbach, the trade group’s vice president of federal affairs in a statement.

But elected officials have talked about leasing public land for data center development in Idaho and Kentucky. A lack of local support can still hinder proposals away from cities and towns, said John Boyd Jr., principal in the site selection company The Boyd Co.

“Companies are regularly looking for some type of public-private partnership, whether it’s sales tax abatements for server equipment or property tax abatements,” Boyd said. “All of those require county, city or state support.”

Most companies that filed prerelease applications with the BLM or have been selected for projects on DOE lands did not respond. Bisnowrequest for comment.

SB Energy In Ohio

Part of a former uranium enrichment plant near the southern Ohio town of Piketon of 2,200 people is planned to become the world’s largest data center to date.

SB Energy, a SoftBank Group company, broke ground on the 189-hectare project in March and committed to building 10 gigawatts of new power plants connected to the local grid. It expects to generate 10,000 construction jobs and 2,000 permanent jobs in the region.

Known as the Portsmouth Site, it includes Department of Energy land. It is divided between public land and some private land, according to an SB Energy spokesperson.

Some yellow excavators and workers in safety equipment are working on a large sand construction site against a blue sky.

Flickr / US Department of Energy

Excavation of the Portsmouth site in 2012 was part of a soil remediation effort at a former uranium enrichment plant

Valar Atomics In Utah

Valar Atomics, a company focused on scaling nuclear energy to power heavy industry, filed an application with the BLM to build a 9,000-acre facility in Carbon County, Utah, NPR reported in September. BLM records confirm the submission but do not contain project acreage.

The development, named Project Beehive, is planned to include a data center along with 456 small nuclear reactors and space to produce nuclear fuel and store nuclear waste at the Department of Energy site.

A Brookfield Partnership In Kentucky

A partnership between Brookfield, NextEra Energy Resources, Big Rivers Electric Corp., Jackson Purchase Energy Cooperative and Paducah Power System this is planning energy generation and AI campus on the 785-acre DOE site.

Construction is expected to be completed at the former Superfund site by 2031, following remediation efforts necessitated by decades of uranium enrichment operations at the site, according to a release from the department.

A spokesperson for Paducah American Energy Hub told Bisnow in a statement that the team is “committed to working with all stakeholders.”

“We have met with many local and state officials and look forward to engaging constructively with them and the community at large,” the spokesperson said.

But Gov. Andy Beshear told Politico in August that the Trump administration excluded him from conversations about the $100B data center project and indicated a willingness to block or delay the data center from opening.

While Beshear can’t prevent data centers from happening, Anozie said, local governments can still make projects difficult to implement once they’re built.

“Where the state might have a way to regulate what’s going on is to use state environmental laws to challenge it and say, ‘Well, you didn’t get a permit for this,'” he said. “But they can’t directly veto or zone out those areas for data centers.”

Amentum and DC Blox In South Carolina

The Savannah River site is one of 16 sites identified by the DOE by April 2025 to support the construction of the necessary data center and electrical infrastructure.

Aerial view of a large industrial construction site with cranes, parking lots, and surrounding green fields and forests.

Wikimedia Commons/Savannah River Site

An aerial view of the construction project at the Savannah River Site in South Carolina in 2012

The site was used to produce plutonium and tritium for nuclear weapons in the 1950s, Spectrum News reported. Efforts at the site are focused on environmental cleanup and managing nuclear material, as well as research and development.

In July, the National Nuclear Security Administration selected engineering firm Amentum and digital infrastructure provider DC Blox to handle building a 1-gigawatt data center and power plant on a 2 GW site. DC Blox told Bisnow has not commented further beyond the publicly available information.

Power Arevia In 3 Countries

Arevia Power, a Las Vegas-based solar and wind developer, has filed preapplication filings on six parcels in Nevada, Arizona and Idaho through LLCs.

In Arizona’s Mohave County, Arevia is proposing a 1,110-acre site at Leo Data Center LLC. Little public information is available, but the mailing address on the LLC’s filing with the BLM shows the same address as Arevia’s office in Glendale, California.

In Idaho, Arevia subsidiary Rhea Data applied in September to build its own 4M SF campus and gas plant on a BLM site southeast of Boise. The development on the 3,700-acre site will be five times the size of Kuna Meta’s 750K SF plant, which opened days before Rhea’s application was announced, the Idaho Statesman reported.

Boise Mayor Lauren McLean said in September that selling off public land for data centers is “shortsighted,” adding that “no data center of this size should be considered anywhere” without a framework to protect the state’s natural resources. Approvals for the Arizona and Idaho projects are pending.

In Lyon County, Nevada, Arevia proposed using four BLM parcels to build a data center campus. It is used by several subsidiaries to apply for swaths of land.

Two have so far been approved: In Mark LLC plans to build a 530-hectare development, and Kimberly Mountain Data LLC has gone ahead to build a 696-hectare campus known as Silver Springs West, Arevia Power Executive Vice President of Lands and Permits Rafik Albert said at a meeting of the Lyon County Board of Commissioners March 19.

Lyon County commissioners expressed concern about the project to Albert, citing insufficient water to support it. Councilors also stressed that Arevia should select private land that has become a data center zone so that the local economy can benefit.

The two remaining entities in Nevada are waiting to see if they have permission to move forward. Silver Springs South LLC is awaiting a ruling on whether it can use the 1,056-acre site, and BLM records also show a Silver Springs North data center application of undisclosed size was filed by Moorman Ridge Data LLC.

Copia Digital In 4 Countries

Copia Digital, a subsidiary of power infrastructure development platform and AI Copia Power, filed a pre-application for six projects on BLM land. The global investment company Carlyle created Copia Power in 2021 and sold the company to the Swedish company EQT in July this year.

Copia has one application in Nevada: a 744-acre data center site northeast of Las Vegas called the Bergen Data Center.

It also filed two proposals in Maricopa County, Arizona, one on a 620-hectare site called the Frontier Data Center and the other on a 999-hectare site called the Tap Data Center. It was filed using a 275-acre site west of Phoenix called the Harquahala Data Center.

In Umatilla County Oregon, Copia filed a pre-application for a Charleston Data Center on a 106-acre parcel.

Copia also filed a preapplication on a 1-hectare site for the Falcon Data Center in Idaho in late January, although county officials told Idaho News 6 in September that they would likely push back on the project due to lack of water and power near the development.

All six applications are pending, BLM records show. A representative for Copia declined to comment Bisnow.

Skylar Capital Management In Nevada

A proposal from an affiliate of Skylar Capital Management is involved in the back-and-forth through the proposed data center on the BLM-owned parcel of more than 80 hectares.

Townsite Solar 2 LLC originally planned to build a solar farm on the site. But in March, the company pivoted and applied to build a data center on the site.

Townsite received permission to move forward with the data center in June. But it didn’t last long: Residents of Boulder City — just a few miles from the site — appealed the BLM’s decision along with environmental advocacy groups the Center for Biological Diversity and the Sierra Club.

That prompted a federal appeals board to halt the project in September, with the board concluding that the BLM may have violated environmental laws by approving the project based on a review prepared for a solar farm instead of a data center, ENR Mountain States & Southwest reported.